70TPD 50% H₂O₂ Project
In cooperation with the owner, he purchased the Swedish engineering company's process package, and jointly improved the third set of 70TPD H2O2 project with our company.
Project Introduction
Construction scale and content
Project construction conditions: | Working with the owner to do the project from scratch |
Schedule time: | From October 2016 to December 2017 |
Schedule planning: | September-December 2016: Determine the process of the project; process package engineering design January-December 2017: The matching of material suppliers is completed; transportation and delivery; water, electricity and ventilation according to the floor plan; main equipment connection; electrical guidance for installation, commissioning and empty running |